Construction of Beach by Sea Dredging – Kalba City
Construction of Beach by Sea Dredging and Coastal Project Works for Kalba City is located in Kalba City, UAE. Main client of the project is Ministry of Public Works and the contractor is Ghantoot Transport and General Contracting LLC. The scope of the work for the project include Dredging, Stockpiling and Beach Formation. Total Dredging Volume is 2,100,00 m3 and the project is still work in progress.
Project Name | Construction of Beach by Sea Dredging and Coastal Project Works |
---|---|
Client | Ministry of Public Works |
Main Contractor | Ghantoot Transport and General Contracting LLC |
Scope of Works | Dredging, Stockpiling, Levelling and Beach Formation |
Location | Kalba City, UAE |
Dredging Volume | 2,100,00 m3 |
Completion Details | 20/11/2016 |
Al Raha Beach Development Project
Al Raha Beach Development Project (Al Dana Infrastructure Phase 1) is located in Al Raha Beach – Abu Dhabi, U.A.E. Main client of the project is Aldar and the scope of the work include Dredging, Stockpiling and Levelling. Total Dredging Volume is 300,00 m3 and the project is still work in progress.
Project Name | Al Raha Beach Development Project (Al Dana Infrastructure Works Phase 1) |
---|---|
Client | Aldar |
Main Contractor | Ghantoot Transport & General Contracting LLC |
Scope of Works | Dredging, Stockpiling and Levelling |
Location | Al Raha Beach - Abu Dhabi |
Dredging Volume | 300,00 m3 |
Completion Date | 29/07/2014 |
Beach Nourishment Works at Abu Dhabi Beach
Beach Nourishment Works at Abu Dhabi Beach is located in Abu Dhabi, U.A.E. Main client of the project is National Marine Dredging Company and the scope of the work include Levelling and shaping of sand to form new beaches. The total length of the beach is 3.5 Kilometers and the project was completed on 15th October 2012.
Project Details
Project Name | Beach Nourishment Works at Abu Dhabi Beach |
---|---|
Client | National Marine Dredging Company |
Scope of Works | Levelling and Shaping of Sand to form new beaches |
Location | Corniche - Abu Dhabi, UAE |
Length of Beach | 3.5 Kilometer |
Completion Details | 15/10/2012 |
Project Images
Digging & Expansion of Sea Channel – Al Sadar Port
Works of Digging and Expansion of Sea Channel in Al Sadar Port is located in Meena Al Sadar – Abu Dhabi, U.A.E. Main client of the project is Command of Military Works, UAE and the scope of the work include Dredging, Reclamation and Re-installation of Navigation Aids. Total Dredging Volume is 4,000,000 m3 and the project is still work in progress.
Project Details
Project Name | Works of Digging & Expansion of Sea Channel in Al Sadar Port |
---|---|
Client | Command of Military Works, U.A.E |
Scope of Works | Dredging, Reclamation and Re-installation of Navigation Aids |
Location | Meena Al Sadar - Abu Dhabi, U.A.E |
Dredging Volume | 4,000,000 m3 |
Completion Details | 24/01/2016 |
Project Images
Beach Development at Umm Al Yafina
Beach Development at Umm Al Yafina Island is located in Umm Al Yafina Island – Abu Dhabi, U.A.E. Main client of the project is Private Affair of H.H Sheikh Mansoor Bin Zayed Al Nahyan. Scope of work for the project include Dredging for Island Formation with Two Approach Channel Works and the total dredging volume of the project is 8,000,000 m3. Project was completed in May 2013.
Project Details
Project Name | Beach Development at Umm Al Yafina Island |
---|---|
Client | Private Affair of H.H Sheikh Mansoor Bin Zayed Al Nahyan |
Scope of Works | Dredging for Island Formation with Two Approach Channel Works |
Location | Umm Al Yafina Island - Abu Dhabi, U.A.E |
Dredging Volume | 8,000,000 m3 |
Completion Details | 27/05/2013 |
Project Images
Dredging & Deepening – Meena Al Sadar, Entr 1
Dredging and Deepening Works at Meena Al Sadar Project is located in Meena Al Sadar – Abu Dhabi. Main Client of the project is Command of Military Works – U.A.E and the scope of work include Dredging, Deepening of Channels, Stockpile and Construction of Breakwater. The total dredging volume is 216,000 m3 with break water works of 305 LM. Project was completed in November 2013.
Project Details
Project Name | Dredging & Deepening Works for Widening Entrance/1 |
---|---|
Client | Command of Military Works, U.A.E |
Scope of Works | Dredging and Stock Pile |
Location | Meena Al Sadar - Abu Dhabi |
Dredging Volume | 331,214,00 m3 |
Completion Details | 27/09/2012 |
Project Images
Dredging & Deepening – Meena Al Sadar
Dredging and Deepening Works at Meena Al Sadar Project is located in Meena Al Sadar – Abu Dhabi. Main Client of the project is Command of Military Works – U.A.E and the scope of work include Dredging, Deepening of Channels, Stockpile and Construction of Breakwater. The total dredging volume is 216,000 m3 with break water works of 305 LM. Project was completed in November 2013.
Project Details
Project Name | Dredging and Deepening Works at Meena Al Sadar |
---|---|
Client | Command of Military Works, U.A.E |
Scope of Works | Dredging, Deepening of Channels, Stockpile and Construction of Breakwater |
Location | Meena Al Sadar - Abu Dhabi |
Dredging Volume | 216,000 m3 |
Break Water Works | 305 LM |
Completion Details | 17/11/2013 |
Project Images
Beach Development at Nurai Island
Beach Development at Nurai Island Project is located in Nurai Island – Abu Dhabi. The main client for the project is Zaya Development LLC and the scope of work for the project include Dredging, Reclamation and Construction of Break Water. The total dredging volume is 6,000,000 m3 and the project was completed in May 2012.
Project Details
Project Name | Beach Development at Nurai Island |
---|---|
Client | Zaya Development LLC |
Scope of Works | Dredging, Reclamation and Construction of Break Water |
Location | Nurai Island - Abu Dhabi |
Dredging Volume | 6,000,000 m3 |
Completion Details | 27/05/2012 |
Project Images
Dredging & Reclamation Works at Al Mirfa
Dredging and Reclamation Works at Al Mirfa Project is located in Al Mirfa – Abu Dhabi. Main Client for the project is National Marine Dredging Company and scope of work for the project was Dredging and Reclamation for Beach Development. The Total Dredging Volume of the Project is 2,700,000 m3 and the project was completed in October 2011.
Project Details
Project Name | Dredging and Reclamation works at Al Mirfa |
---|---|
Client | National Marine Dredging Company |
Scope of Works | Dredging and Reclamation for Beach Development |
Location | Al Mirfa - Abu Dhabi |
Dredging Volume | 2,700,000 m3 |
Completion Details | 01/10/2011 |